Water damage · Land O’ Lakes, FL · December 2025
A second-floor leak that came through the kitchen ceiling of a new Land O’ Lakes home
Water was dripping onto the kitchen island when we arrived, and five rooms upstairs read wet. The house had no power yet. Eight days later, every moisture point we logged was at or below its dry goal.

What we found
The house was a new two-story home that was still under construction. When we arrived that evening, water was dripping from the ceiling above the kitchen island and the living room onto the laminate floor and the island countertop. We got the water off the floor right away and protected the cabinets.
Upstairs, the water was concentrated in one corner, where the master bedroom, master toilet room and two closets share a wall with the hall bathroom. All five rooms had wet readings on the floors and walls.
What we did
We removed the baseboards in every affected room upstairs and cut small inspection holes in the walls of four of the five rooms so the wall cavities could dry. Two holes were cut in the kitchen and living room ceilings to trace the leak, and the wet ceiling drywall in the kitchen came out.
The house had no power yet, only one outlet at the junction, so the first night we set as many air movers as that circuit could run. We came back the next morning to meet the contractor and plumber. Once the house was energized, we added more air movers on the first floor.


Kitchen ceiling drywall readings
Meter reading at each visit. The dashed line is the dry goal of 17.
Source: Tidal drying log for this job, recorded in Albi.
How we knew it was dry
- December 18 · After-hours call. Water extracted, cabinets protected, baseboards pulled, air movers set on one available outlet. Indoor conditions 75°F and 91% relative humidity.
- December 22 · House energized, more air movers added downstairs. Kitchen ceiling down to 22, upstairs points at 17 to 19. Humidity down to 64%.
- December 26 · Every moisture point at or below its goal. Equipment pulled and the house ready for build-back.
Every moisture point we logged on this job:
| Room | Surface | Start | Dec 22 | Dec 26 | Goal |
|---|---|---|---|---|---|
| Kitchen | Ceiling drywall | 100 | 22 | 13 | 17 |
| Master bedroom | Floor | 100 | 19 | 15 | 17 |
| Master toilet room | Wall drywall | 100 | 19 | 14 | 17 |
| Master bath | Wall drywall | 60 | 19 | 14 | 17 |
| Master bath closet | Floor | 100 | 17 | 14 | 14 |
| Guest bedroom | Floor | 100 | 17 | – | 17 |